Hospital Management Activities

Hospital Management Activities

New Development Projects were included in ADP FY 2022-23

S# Name of the Projects Estimated PC-I Cost
(Million)
Allocation 2022-23
(Million)
Remarks
1 Establishment of Cardiac Center, Installation of 11KV Line and construction of boundary wall with DHQ Hospital Bagh 84.784 25.000 Estimates to be revised by PWD Bagh according to up dated CSR/ in process
2 Construction of 50 Beds Wards with Bhimber AJK 157.199 20.000 PC-1 submitted in P&DD. Scrutiny observation received from P&DD. Estimates to be corrected by PWD Bhimber/ in process. Pre DWP to be conducted
3 Construction of 200 Beds Wards with Kotli AJK (Phase-I) 729.149 50.000 PC-1 submitted in P&DD. Scrutiny observations received from P&DD
4 Construction of Doctors & Nurses Hostel and Boundary Wall with Haveli AJ&K 119.729 20.000 PC-1 submitted in P&DD. Scrutiny observations received from P&DD. Estimates to be corrected by PWD Haveli Kahuta/ in process. Pre DWP to be conducted
5 Construction of THQ Hospital khuiratta District Kotli AJ&K 350.000 45.000 Cost estimates prepared by PWD Building Kotli received. PC-I preparation in process
6 Construction of THQ Hospital kail District Neelum, AJ&K(Phase- I) 350.000 40.000 Geo tech survey pending due to land dispute. CDO has been asked to conduct Geo tech survey as DHO Neelum has conveyed the consent of land owners
7 Construction of 200 bedded Hospital and trauma center Muzafarabad AJ&K 750.000 130.000 Topographic Survey done by CDO. Preliminary Design prepared by CDO. Finalization of design in process
8 Provision of Life Saving Services in Major Hospitals of AJ&K and Consumable for RBTC Mzd) for FY 2022-23 150.00 150.00 PC-1 approved by AKDWP forum on 20-10-2022. Admin approval issued
9 Provision of ambulances( fully equipped) 10 Nos in AJK 100.00 20.00 Pre DWP meeting conducted on 15th September 2022. Amended PC-I submitted soon in P&DD
Total 2790.861 500.000